Building DC2 : Work continues!
(Last Update, may 16th 2006)
The work on our new Datacenter (iWEB-CL) goes very well. The first phase of installation of the electrical panels follows its court. Once finished, these panels will be able to support a load of 600V/600A which will be used to feed the first colocation cabinets and dedicated servers racks.
In preparation for the installation of the suspended ceiling, the modification of the sprinkler system also began. It will be equipped with the preaction system which will be use to avoid the accidental water discharge.
The first cable racks were also received in preparation for their installation in the next weeks. They will be used to support the kilometers of cable that will feed the Datacenter.
————————————
April 10th, 2006
The work on our new Datacenter (iWEB-CL) does not cease advancing. The first phase of painting has been done in the telco room, the electric room, the colocation and dedicated section. There will be only the offices section left to begin. The installation of the cable racks is almost finished thus all the colocation section and the first dedicated section was finalized. The only remain thing to do is to connect everything to the telco room.
————————————
April 21th, 2006
The work on our new Datacenter (iWEB-CL) is still in progress. The first optical fibre link of the Vidéotron Télécom supplier made its appearance and for the following weeks, other suppliers will make their entrance. The electrical connectors were installed on top of each site where will be laid out the first shelves, also the electrical panels were installed at the end of the rows of shelf on the dedicated servers side. On the colocation side, the installation of the electrical panels also began. In regards to the ”Telco” room, the installation of the hanging ceiling began and the rails for wiring were installed.
————————————
May 8th, 2006
Work at our new Datacenter (iWEB-CL) is still under development. New circuits for 10 full racks and 20 half racks have been installed. Work on the ceiling plumbing system for air-conditioning is in progress and the installation of the raised floor and the ceiling will be completed in the next days. The dry cooler has been delivered and a flagstone in concrete has been installed in order to fix the generator and the dry cooler. We will also be installing a temporary 200kvA UPS while waiting for the arrival of a new 300kvA. Everything takes place as expected so that the installation of the first servers can be made near June 1th.
————————————
May 16th, 2006
Work at our new Datacenter (iWEB-CL) do not stop. Last week, two new air conditioning units have been received (22 tons and 30 tons). Work in the Telco room is about to be finalized, the rail racks are fixed and the electricity work is almost completed. Two Cisco 6509 routers also made their entrance and they are presently in the Telco room of the iWEB-HD datacenter ready to be configured. The dry cooler has been fixed on the flagstone in concrete.
These pictures have been taken a month and a half ago.

These pictures have been taken a month ago.


These pictures have been taken 3 weeks ago.


These pictures have been taken a 2 weeks ago.


These pictures have been taken a week ago.


These pictures have been taken a few days ago.


We will post more details and new pictures next week!

Blog
Forum
Status


May 4th, 2006 12:37 am
Hey, is there an ETA for the new DC and whether servers from the old center will be moved there ?
May 4th, 2006 7:41 am
Servers from the old center will not be moved there. We should be able to start offering spaces & servers in the new datacenter starting June 1st !
May 17th, 2006 9:29 am
I see you’re having some problems with comment spam. You might want to look into Spam Karma 2 since I know you’re running WordPress…
http://unknowngenius.com/blog/wordpress/spam-karma/
If you do decide to do it, make sure you turn off the encrypted payload portion since that causes just about everything to be flagged as spam…
May 18th, 2006 4:29 pm
We already use Spam Karma …. but something must have gone wrong and we missed those spam. I just moderated the spams and everything should be clean now, I also raised the security level of Spam Karma.
May 31st, 2006 8:25 am
My company is also building a second Data Centre. Did you encounter any problems with your new DC as it was being planned or initiated?
May 31st, 2006 10:00 am
Everything went almost 100% as planned!
February 22nd, 2008 6:53 pm
Well what the new place look like?
small bulding,lol…