Datacenter Expansion; Connection in progress!
Here are the latest pictures of the work in progress at iWEB’s-CL DC. At the moment, electrical cabling work is in progress; connection of the new electric 6000A entry, connection of the new 1.5MW generator that replaces the temporary 1MW generator installed a few weeks ago; plumbing work on the water lines and the water tower which will allow the connection of the air conditioning units to the water lines.
Did you miss our last publication of the work in progress at iWEB’s-CL data center?
You may consult the previous publication here.
| Zone6: Fuel tank | |
| Here’s a picture of the fuel tank delivered some days ago. The tank will be connected to the new 1.5MW generator in the next few weeks. Here are some interesting facts about the fuel tank:
- Capacity: The tank has a 9171 US gallon capacity. |
|
| Zone6: Ventilation ducks and water tower plumbing | ![]() |
| Here’s a picture of the work in progress of the plumbing on the water tower lines and the work on the ventilation system. Ventilation ducks were set up above the water tower and the work should be completed this week. The connection of the water lines continues and should be finalized soon. | |

New pictures will be published to keep you up to date with the last developments of the other sections.