Datacenter Expansion; Phase 2 almost completed!

Published on July 17, 2007 at 4:54 pm by iWeb-SDelisle in: iWeb

dedicated small Here are the latest pictures of the work in progress at iWEB’s-CL DC. We are proud to announce that the work on our iWEB-CL data center is almost completed and we plan to finalize everything during the month of August.

The work on our data center has completely stopped since yesterday because of the construction holiday, which is 128 000 construction workers of Quebec on vacation for two weeks, and will start again on July 30th. To complete phase 2, asphalt work outside must be executed and we have to set up control and surveillance processes on all our equipments. Quick scoop, phase 3 is already in preparation!!

Last week, we announced some work going on on our new 1.5MW generator and our 500KW UPS thus both are now completely functional. Today, we shall proceed with the start up of our two air conditioning units of 30 ton each located in our dedicated servers zone.

Did you miss our last publication of the work in progress at iWEB’s-CL data center’
You may consult the previous publication here.

Zone 1: Dedicated Servers dedicated zone
Zone 2: Colocation colocation zone
Zone 2: Colocation (Telco room) telco zone
Zone 3: Electrical room salle electrique
Zone 7: Hydro electrical room salle electrique hydro
Zone 6: New section (Water tower) agrandissement

phase2

New pictures will be published to keep you up to date with the last developments of the other sections.

Comments

  1. [...] September 2006 | March 2007 | April 2007 | May 2007 | June 2007 | June 2007 | July 2007 [...]

About the iWeb blog

The iWeb Blog covers web hosting, web development, web design, Internet marketing and just about every announcement concerning iWeb.